The second excavator EKG-15M began working on the gold quarry Bakyrchik in Kazakhstan

Manufacture and supply of excavator was carried out within the contract signed in October last year with the company too "Bakyrchik mining enterprise" (management company JSC "Polymetal").

The contract includes the manufacture, supply and a turnkey installation of five machines EKG-15M. The first machine started working in April 2016, the second in May.

The installation was carried out under the guidance of IZ-KARTEX service engineers. Installation work for each machine accounts for 80 calendar days according to the contract, and the excavator was ready to work accurately within the contractual terms. At the moment the third machine is being installed, which is planned to finish by the end of June 2016.

To ensure smooth running of equipment on the territory of Kazakhstan, a subsidiary enterprise LLC "IZ-KARTEX KAZAKHSTAN-SERVICE" was created in Astana.