Nine IZ-KARTEX shovels started working at mining enterprises in the second quarter 2018

Nine IZ-KARTEX shovels started working at the mining enterprises of Russia and CIS countries from April to July 2018.

From April 3, 2018 to May 12, 2018 two EKG-10 started working in India. There are 5th and 6th  shovels in Eastern Coalfields Limited under the agreement. The installation was made by DDP-N-COMPANY with participation of IZ-KARTEX in chief installation, adjusting of low-voltage package and installation of Automated Lubrication System.

From April 9, 2018 to May 29, 2018 four IZ-KARTEX shovels were commissioned in Uzbekistan at Alamlyc MMC: two EKG-10 and two EKG-15M.  The installation was made by Almalyc MMC  with participation of IZ-KARTEX in chief installation, adjusting of low-voltage package and installation of Automated Lubrication System.

On May 17, 2018 the first EKG-10 over the past 25 years was commissioned at Magnitogorsk Iron and Steel Works. Specialists from IZ-KARTEX made the adjusting of main and auxiliary electric drives and chief installation. Service Company of Magnitogorsk Iron and Steel Works made the installation. 

On June 21, 2018 the EKG-12K started working at SSGPO. This is the 2nd shovel under the agreement. Kazspetssnabservıs made the installation with IZ-KARTEX participation in chief installation, adjusting of low-voltage package and installation of Automated Lubrication System.

On May 29, 2018 the EKG-15M started working at Bakyrchık mining enterprise in Kazakhstan. This is the 5th machine at Bakyrchik under the agreement.  Kazspetssnabservıs made the installation with IZ-KARTEX participation in chief installation, adjusting of low-voltage package and installation of Automated Lubrication System.